Gazprom Invests RUB 400 Million in Dagestan's Infrastructure
31
1 минута
In Dagestan, Gazprom will restore gas supply facilities with a total length of over 3 km. Due to the unsatisfactory condition of 12 gas infrastructure facilities in Dagestan with a total length of 35 km, they will undergo reconstruction. The work will be carried out by a regional subsidiary of Gazprom.
Gazprom has already commissioned 2 facilities:
• High-pressure gas pipeline in the settlement of Semender - 613.2 m
• High-pressure gas pipeline to Bread Factory No. 2 - 2,300 m
By January 2026, six more facilities will become operational:
• High-pressure gas pipeline at the "Severnaya" GRS - 812 m
• Gas pipeline from the Makhachkala GRS to GRP-6 - 1,180.7 m
• Gas pipeline to Maternity Hospital No. 2 - 1,727 m
• Gas pipeline to the peak-load boiler house - 1,380 m
• Gas distribution network in the village of Kirovaul - 1,380 m
• High-pressure gas pipeline Komsomolskoye - Sultanyangiyurt - Nechaevka - 13,900 m
Four more facilities are currently under review by approving authorities. The total project cost amounts to RUB 400 million.