Energy Production in Dagestan Grows by Nearly 6% in 2025
By the end of 2025, electricity generation in Dagestan reached 5.395 billion kWh, an increase of 298 million kWh (+5.85%) compared to 2024.
Found: 18 results
By the end of 2025, electricity generation in Dagestan reached 5.395 billion kWh, an increase of 298 million kWh (+5.85%) compared to 2024.
The first is the construction of a new grain terminal with an annual capacity of up to 1.5 million tons, with equipment scheduled for delivery in Ju...
The strategy sets a target to increase this number to 367 exporters by the end of the decade.
In anticipation of winter loads, Sultanov also revealed plans to replace thirty transformers across the region.
The top manager noted that passenger traffic was projected to increase by 5% in 2025, amounting to 3 million passengers compared to 2024.
By the end of 2025, these projects are expected to contribute to a reduction in the electricity deficit by 1.5 trillion kilowatt-hours in Dagestan.
In response, Dagestan plans to construct two new substations aimed at providing additional power to the city of Makhachkala.
It operates 208 substations with a capacity of 35 to 110 kilovolts and approximately 5,000 kilometers of transmission lines with the same capacity.
As part of the program to reduce the risk of power outages for consumers by the end of 2024, it is planned to increase the capacity of 25 substations,
The first phase of the project is expected to be completed by the end of 2024.
outages for consumers, the Ministry of Energy of the Russian Federation plans to install and replace 38 transformers in 2024, increasing capacity by 3...
The facility is scheduled for completion by the end of 2024.
121 out of 207 substations of 35-110 kV operated by Dagenergo are overloaded.
By the end of 2023 it is planned to complete the assembly of two more prototype aircrafts.