Rosseti reconstructs substation in Dagestan for RUB 645 million, increasing its capacity in 2.5 times

402
1 минута

Rosseti Northern Caucasus PJSC reconstructed the Yaryksu 110 kV substation, which supplies electricity to consumers in Khasavyurt and the nearby Novolaksky municipal district of Dagestan. The project cost more than RUB 645 million.

The facility was equipped with power transformers manufactured in Russia. This allowed for a significant increase in capacity, from the initial 50 to 128 MVA, a two-and-a-half-fold increase.

This enhancement in capacity will effectively mitigate the risk of equipment overload during the upcoming summer period. The work was accomplished as part of an initiative aimed at enhancing the reliability of the distribution network system in Dagestan.

Rosseti Northern Caucasus PJSC is responsible for transmitting electricity through networks operating at voltages ranging from 0.4 to 110 kV. Additionally, they provide services for the technological connection of customers to the infrastructure of the grid of the North Caucasian Federal District.