More than RUB 600 million to be spent in Dagestan to repair bridge on federal motorway

250
1 минута

In the Republic of Dagestan, a bridge over the Ulluchay River, located at the 907th kilometer of the federal highway R-217 «Kavkaz», is undergoing a comprehensive overhaul. Currently, efforts are underway to identify a contractor for the project.

The estimated cost of the project exceeds RUB 605 million. The announcement of the tender results is scheduled for December 4th. According to the published documents, the contractor is expected to complete the work by November 13th, 2026.

Among the tasks to be accomplished are the construction of temporary crossings, the dismantling of the existing bridge and approaches, the installation of supports and spans, provision of electrical lighting and implementation of other works as specified in the contract.

It should be noted that approximately 35,000 vehicles cross this bridge daily.